The Meadowlakes Community Center Project continues to move forward.
Doors and electrical components have been installed at the golf cart facility, with construction on the temporary pro shop/permanent golf cart office expected to be completed within six to eight weeks. 100% construction designs for the community building and pool portions of this project are anticipated within the next week, and July 15 has been targeted as the meeting date where Meadowlakes City Council will vote on the authorization of bid invitations for subcontractors to be advertised.